Schedule budgeted work on the Scheduler


Budgeted work that needs to go into someone's diary appears in the Scheduler's Budgets tray at the right point in the workflow. You drag it from the tray onto a person's row to book it, and Glide keeps track of how much of the budget has been scheduled.

When does budgeted work appear in the tray?

A job's budget line appears in the Budgets tray when all of these are true:

  • the line's section has On Scheduler set to Yes - In office or Yes - Client site;
  • the job has moved past the section's Allocation Stage (or the section has no Allocation Stage);
  • the line is Active;
  • the job is not complete or deleted.

See Budget template sections: every setting explained for how to set these up.

Example: on Tony & Co Architects' accounts job, Information chased/received has been completed and the job is now waiting at To allocate job and plan dates. Fieldwork's Allocation Stage is Information chased/received, so the Fieldwork budget (2,250 minutes for the Preparer) is now in the tray. The other sections are set to No, so they never appear in the tray.

Open the Budgets tray

  1. Open the Scheduler from your practice-name menu.
  2. Click Budgets in the top-left corner. The tray opens on the left. Click it again to close the tray.

The Scheduler with the Budgets tray open, showing one item: TON-077 Tony and Co Architects - Accounts and CT - 31/07/2025, Fieldwork - Accounts preparation (2250 min)

Tray filters

Setting What it does
Sub-System Show work for All sub-systems, or only one. The list shows each sub-system with an active budget template.
Office Shown if you use multiple offices. Choose My Office, All offices or a specific office.
Scope: Held Only work on jobs that you currently hold.
Scope: Linked Work on jobs you hold, or where you are named in any of the job positions (for example Partner, Manager or Preparer).
Scope: Overall All budgeted work that is ready to schedule.
Hide fully scheduled items Ticked by default. Hides a line once the time booked for it reaches its budgeted minutes, so the tray only shows work still to be booked. Untick it to see everything.

Under the filters, Glide shows how many items are listed and how many are hidden.

Reading a tray item

Each item shows the client code and name, the workflow system and job date (for example TON-077 Tony & Co Architects - Accounts & CT - 31/07/2025), then the section, description and budgeted minutes (for example Fieldwork - Accounts preparation (2250 min)). Once some of the work has been booked, it also shows how many bookings there are and the booked minutes against the budget, for example [Scheduled: 1x, 2250/2250 min].

Book the work

Drag from the tray

  1. Find the item in the tray.
  2. Drag it onto the row of the person who will do the work, at the date (and, in a time view, the time) the work should start.

Glide creates one Scheduler entry for that person, linked to the client and job, for the minutes the line still has to book. If that is at least a full working day, the entry covers as many of the person's working days as the minutes need, using their work pattern, and its start and end times show how much of the first and last day it takes. For example, a 2,250-minute (37.5-hour) budget dropped on a Monday becomes one all-day entry from Monday to Friday. Any linked job rules you have set up in Scheduler Settings also run.

  • Part days: if the minutes don't fill the last day, the entry ends part-way through it. A 2,000-minute budget dropped on a Monday runs from Monday to 12:20 on Friday: Monday to Thursday count as full days and Friday as 3h 20m. The capacity reports count 2,000 minutes, not five full days. Part days are measured on a working day of 09:00 to 13:00 and 14:00 to 17:30, scaled to the person's hours. With pro-rata heights switched on, the entry is cut down to its share of the part day, so the rest of that day stays free for other entries; otherwise the part day is shown lighter with its time.
  • Non-working days: days that aren't in the person's work pattern, such as weekends, count as nothing. An entry that runs over a weekend stays one entry, so you only ever have one thing to drag. A day off in the middle of an entry, such as a Tuesday the person doesn't work, is shown with grey diagonal stripes behind the entry's text, so you can still read the client and job while seeing they aren't in that day. Work you book on a day the person doesn't normally work, such as a day off or a weekend, still counts towards the budget: a timed entry counts its length, and a whole day counts as one of their usual working days. It doesn't count towards their capacity.
  • Afternoon start: drop the item on an afternoon cell in the Half Day view and the entry starts at 14:00, with only the afternoon of that first day counted. In the 15 Mins view it starts where you drop it.
  • Less than a day: the entry is a timed entry. In the 15 Mins view it starts where you drop it; otherwise it starts at 09:00 (14:00 on an afternoon half-day cell).

Hover over the entry to see its dates and working time, for example Mon 16 Nov 2026 - Fri 20 Nov 2026 12:20 ยท 33h 20m. Bank holidays and existing holiday entries are not taken into account, so check the dates.

Because Hide fully scheduled items is ticked and the whole budget has now been booked, the item drops out of the tray. Untick the box to see it again with its scheduled time:

You can book a line in more than one piece, for example two days with one person and a day with another. Drag it again for each booking (untick Hide fully scheduled items first if the full budget is already booked) and resize each entry. The tray shows the total booked against the budget.

Right-click an empty slot

Right-click an empty slot on a person's row and choose Add new budget linked event. Pick the budget line from the list (it uses the tray's current filters and includes fully scheduled lines) and click Create. The entry uses the time you selected, rather than the budgeted minutes. The time booked against the budget is the working time in your selection (using the person's work pattern, so a selection of whole days counts each day's working hours), even if that is more than the budget.

Link an existing entry

If you have already booked the work as an ordinary entry for the client or job, right-click it and choose Link to budget allocation. Pick the budget line from the client's budget allocations and click Link to Budget. The time booked is the entry's working time. This option is not offered for holiday, sickness or training entries, or for entries that are already linked.

After scheduling

  • The booking appears under its budget line on the job card and on the job's budget page, with the person's initials and the dates and times booked, and counts towards the Scheduled Total. See View and edit a job's budget.
  • Moving an entry keeps its booked time. Glide moves the end so the entry still covers enough of the person's working days: a Monday-to-Friday entry dragged to Wednesday runs to the following Tuesday. Drag it onto someone else's row and their work pattern is used. An entry booked only on days off stays where you drag it.

    Resizing an entry changes its booked time to the working time it now covers, even if that is more than was budgeted: the budget then shows more time scheduled than budgeted. Shorten a Monday-to-Friday entry to Monday-to-Thursday and one day's time returns to the tray.

  • Deleting the entry removes the booking, and the line returns to the tray if it is no longer fully scheduled.

Coming soon: started and completed work on the Scheduler

The Stage Started and Stage Completed settings on each section tell Glide when budgeted work has been started and finished. A future release will use them to flag on the face of the Scheduler which booked work is unstarted, started and complete. Recording actual time against budget lines is due for release in November 2026.